Record changes
Record a change
Section titled “Record a change”- Open the dashboard of the site.
- Press C, or open Do and select Record a change.
- Write what you changed.
An agent with write access can record a change with the MCP tool record_change.
How Checkend calculates the result
Section titled “How Checkend calculates the result”Checkend compares the average per day after the change with the average per day before it. Both sides have the same number of days, from 3 to 7. The metric is visitors, or the metric that you give with the change.
| Result | Difference |
|---|---|
| Up | 5% or more above |
| Down | 5% or more below |
| No clear change | Between these values |
There is no result in the first 3 days. The result shows what happened after the change. It does not prove that the change was the cause.